Richmond Build Update

1870_main.jpg

Dear Power Women,Volunteers and Partners

I regret to inform you that our ground-breaking date for 8180 Ash Street has been postponed to the fall of 2015 due to the municipal application process.

Unfortunately, the feedback received from the community on house design and vehicle manoeuverability in parking areas has resulted in the denial of our Development Variance Permit application; thus forcing us to reconsider the calendar for our build in Richmond.

Also, we have been instructed by the City of Richmond to further our consultation with the local community. Hence, we will be holding a Public Information Meeting on May 12th at Debeck Elementary School, 8600 Ash Street from 6:30 to 8:00pm.

We will resubmit our application before the Development Permit Panel on June 24th and before City Council on July 13th.

I take this opportunity to personally thank you for your continuous support and patience.  We are thrilled by the interest our new build project has garnered. All across Metro Vancouver, Power Women and their supporters are taking a stand for affordable homeownership.

Though we are eager to break ground and put families into homes fast, we understand that sometimes the municipal approval process can be challenging. We are now more than ever determined to address all issues and inquiries in order to allow for a build date in late fall.

We thank you for your continuous support and patience and look forward to seeing you on our build site.

 

Sincerely,

Tim Clark

CEO

Joe Norman